Six large scale renewable energy projects to meet 70% targets by 2030



The progress of six large scale renewable energy projects was reviewed with the developers including Ceylon Electricity Board (CEB), Sri Lanka Sustainable Energy Authority (SEA) and the Power and Energy Ministry officials yesterday to achieve the Government policy of 70% renewable Energy targets by 2030.

Issues related to Government approvals, land acquisition, construction of transmission lines, grid concurrence, power purchasing agreements, financing, implementation timelines of the projects was discussed.

500 MW wind project in Mannar Pooneryn by Adani Green Energy to be completed by January 2025 with the construction of a 400Kv transmission line and necessary approvals and Power Purchasing Agreements by end of September 2023.

700+ MW Ground Mount Solar with Battery storage in Poonakary. 134MW directly to be connected and operate with battery storage. To commence work in March 2024 with necessary approvals for transmission lines.

150 MW Ground Mount Solar in Hambantota by a consortium of local developers. Build with transmission lines to be completed by December 2024. Can go up-to 300 MW with investment.

100 MW Ground Mount Solar in Siyambalanduwa with Battery storage by the Consortium of Lakdhanavi Limited, Wind Force PLC & Blue Circle Pte Ltd to be completed by the end of 2025.

100 MW Ground Mount Solar in Baticaloa by Solar Forge to be completed by 2025 with necessary approvals & construction of transmission line by October 2023.

130 MW Ground Mount Solar in Sampur by the Joint Venture of CEB & NTPC of India.

To be completed in 2 stages with construction of 2 transmission lines & first phase of 50 MW by 2025 funded by AIIB, NTPC and CEB. (Chaturanga Pradeep Samarawickrama)

 