The action of the engineers in charge of the Upper Kothmale reservoir in emptying the reservoir as from Wednesday has resulted in a complete shutdown of the hydro electricity supply from this power plant.
At present, 150 megawatts of electricity is added to the national power grid from this plant.
The engineers said this step had been taken to attend to an urgent inspection of the reservoir bund and the reservoir. Filling of this Kothmale reservoir began in April last year, and with the current emptying it has been observed that a large amount of silt deposits lying at the bottom of the reservoir.
The villagers said they were amazed to see this reservoir had so much silt even before completing one year of its opening, and expressed fears that at this rate, they foresee a danger that at the end of next five years the reservoir would fill up completely with silt.
The villagers also said they suspected the decision to empty the reservoir had been taken due to seepage of water from the bund.
However, the engineers said this action was routine and had been taken to inspect the reservoir and the tunnels as it was one year since water had been filled up in the reservoir. (Gamini Bandara, Illanganthillake, and Ranjith Rajapakse)
Comments - 4
Comments - Upper Kothmale reservoir emptied
ss Friday, 22 March 2013 01:25 AM
bend over villagers. Colombians need power for their gadgets. your property damage is secondary.
06
Ranjit. S Friday, 22 March 2013 01:51 AM
The reservoir may have weeped a lot after getting the new minister.
17
ANTON Friday, 22 March 2013 07:20 AM
ANCIENT KINGS FILLED RESERVOIR WITH WATER, THESE PEOPLE ARE EMPTYING.
01
TERRENCE DE SILVA Saturday, 23 March 2013 04:15 AM
Another Engineering marvel!
00
222
Add comment
Comments will be edited (grammar, spelling and slang) and authorized at the discretion of Daily Mirror online. The website also has the right not to publish selected comments.