Colombo, January 1 (Daily Mirror) - Nearly 40 per cent of the Kadawatha–Mirigama stretch of the Central Expressway has been completed so far, Transport, Highways and Urban Development Minister Bimal Ratnayake said today.
The Minister instructed officials to pay close attention to traffic congestion issues previously identified along the Colombo–Kandy road and at expressway entry and exit points during the construction process, in order to minimise inconvenience to motorists.
He made these remarks while inspecting the ongoing development work on the Kadawatha–Mirigama section, which is the first phase of the Central Expressway project.
Although agreements for the project were signed in 2015, construction began only in 2020. However, the work was later completely stalled due to the severe economic crisis caused by failed economic policies, officials said.
Following the appointment of the new government, discussions were resumed between the Ministry of Transport and the Chinese government, resulting in the approval of a loan to complete the remaining work. Construction activities were subsequently restarted on September 17, 2025.