Last Updated : 2024-04-26 08:55:00
The Attorney General has declined to issue a generation license to the Ceylon Electricity Board (CEB) for the purchase of electricity from a 400-megawatt power plant installed in a Turkish ship citing several procedural defects.
The AG has pointed out the absence of a tender procedure and the government not owning the shares of the power plant as procedural flaws.
It has been calculated that the price that has to be paid to this power plant would be Rs. 43 per unit and it has been allowed to import fuel directly from oil-exporting countries due to which the government would lose the fuel import tax.
CEB trade unions have pointed out that the tax money that the government would lose in this manner would be Rs. 15 billion a year.
Meanwhile, it is learnt that the Sri Lanka Ports Authority has not given permission for the ship to enter into the Colombo Harbour. The plan to purchase electricity from a Turkish floating power plant was mooted after the Turkish Ambassador to Sri Lanka had told the Power and Energy Minister in February that his country could provide electricity to Sri Lanka and that his country had ships with power plants for the purpose. (Dayaseeli Liyanage)
Consumer Monday, 29 July 2019 10:34 AM
What has AG got to do with this?
Add comment
Comments will be edited (grammar, spelling and slang) and authorized at the discretion of Daily Mirror online. The website also has the right not to publish selected comments.
Reply To:
Name - Reply Comment
US authorities are currently reviewing the manifest of every cargo aboard MV
On March 26, a couple arriving from Thailand was arrested with 88 live animal
According to villagers from Naula-Moragolla out of 105 families 80 can afford
Is the situation in Sri Lanka so grim that locals harbour hope that they coul