The Ceylon Electricity Board (CEB) said that it had restored the power interruption in the Colombo area a short while ago.
Energy Ministry Secretary Dr Suren Batagoda said as he was informed by the CEB engineers, it was identified by them as a software malfunction.
However, after five hours, the power was restored in the Pannipitiya, Dehiwela, Sri Jayewardenepura and Ratmalana areas.
Power was interrupted in Pannipitiya, Dehiwela, Sri Jayewardenepura and Ratmalana this morning due to the tripping of Pannipitiya - Biyagama 220 kV transmission line at about 7.20 a.m.
BuffaloaCitizen Tuesday, 15 May 2018 12:57 PM
Software cannot malfunction, it is logic based, thus unless an incorrect logic input was given or a warning from the software was not hindered, then the software itself will open or close a system. However in a country of majority fools, this will be believed.
Wow123 Tuesday, 15 May 2018 03:44 PM
Never heard of a thing called software bugs? Guys like you won't help to build a nation. Always trying to blame someone.
Ex-Pat Wednesday, 16 May 2018 08:37 AM
Anyway, if the software was the problem, consider new underwear or hardware? After all, we have so many hardware shops all over!!!
BuffaloaCitizen Wednesday, 16 May 2018 09:05 AM
Wow123, a software bug cannot down a 220kV line, it will give ample warning before that happens. Further, the software is well tested on its logic b4 commissioned into such critical applications. Don't compare blooming Windows software to those used in critical industrial applications.
Unchikun Tuesday, 15 May 2018 01:06 PM
As an IT engineer this explanation is very serious. If it is a software malfunction it may or will occur again. I think it may have been a human error. No one admits this error.
mahinda Tuesday, 15 May 2018 04:22 PM
this is all bullshit . I am from dehiwela and power failed at 3.30 am in the morning and restored at 5.30 am. Again it failed at 7.10 am and restored @12 in the afternoon . We were informed by saumya kumarawadu its due to high tension cable failure . Personally i think its sabotage CEB engineering mafia where kumarawadu is the unoin leader !!! And they are on a work to rule !!!
Add comment
Comments will be edited (grammar, spelling and slang) and authorized at the discretion of Daily Mirror online. The website also has the right not to publish selected comments.
Reply To:
Name - Reply Comment
US authorities are currently reviewing the manifest of every cargo aboard MV
On March 26, a couple arriving from Thailand was arrested with 88 live animal
According to villagers from Naula-Moragolla out of 105 families 80 can afford
Is the situation in Sri Lanka so grim that locals harbour hope that they coul
03 May 2024